Line Construction Criteria

  1. Electrical Lines will be constructed according to priority serial no. of the Master Plan.

  2. The minimum qualifying revenue is Tk.45,000.00 (Taka Forty five thousand only) per year per kilometer.

  3. The minimum qualifying revenue is Tk22,500.00 ( Taka Twenty two thousand five hundred only ) per year per kilometer for line conversion. If line conversion is required for system improvement then that revenue criteria will not be applicable but prior approval from System Engineering and Design Directorate will be needed.

  4. The anticipated revenue for different types of consumers are as follows:

Sl. no

Type of Consumer

Annual Revenue

i)

Domestic (Load up to 1KW)

Tk.1,000.00

ii)

Domestic (If load is more than 1KW) per KW

Tk.1,000.00

iii)

Commercial (Load up to 1KW)

Tk.1.800.00

iv)

Commercial (If load is more than 1KW) per KW

Tk.1.800.00

v)

STW/LLP (Load up to 7.5 HP)

Tk.6,000.00

vi)

STW/LLP (If load is more than 7.5 HP)

Tk.15,000.00

vii)

DTW (If load is less than 25 HP)

Tk.15,000.00

viii)

DTW (If load is 25 HP or above)

Tk.30,000.00

ix)

Rice Mill/Saw Mill/Oil Mill/Flour Mill (3 Phase load up to 20 HP)

Tk.25,000.00

x)

Rice Mill/Saw Mill/Oil Mill/Flour Mill (3 Phase, If load is more than 20 HP but less than or equal to 40 HP)

Tk.35,000.00

xi)

Rice Mill/Saw Mill/Oil Mill/Flour Mill ( Single Ф)

Tk.14,000.00

xii)

Annual required revenue Tk.1,000.00 (One thousand only) per year per Kilowatt of load for small industries or general power (Except Rice Mill/Saw Mill/Oil Mill/Flour Mill ) upto 30 KW. & for CI Connection Annual required Revenue Tk.1,000.00 Per KW.

x)

Annual required Revenue for Large Industries or general power will be Tk.1,000.00 (One thousand only) per year per Kilowatt of load for upto 30 KW & above 30 KW additional per kilowatt per year of load Tk.2,000.00






More information at http://www.reb.gov.bd/Citizen Charter