সর্ব-শেষ হাল-নাগাদ: ৯ মে ২০২১

এক নজরে বাপবিবোর্ড এর কার্যক্রম

                                                                                                         (as on March' 2021)

 

1

Total PBSs

80 Nos.

2

Approved Projects

81 Nos.

3

District included in RE program

61 Nos.

4

Upazillas included in RE program

462 Nos. (461 On-grid & 01 Off-grid)

5

100% Electrified Upazillas

288 Nos. (Opening Completed)

173 Nos. (Waiting to inaugurate)

6

Villages included in RE program

84,800 Nos.

7

Villages Electrified

84,460 Nos.

8

House Hold in Program Area

2,51,68,763 Nos.

9

Population in Program Area

10,68,93,673 Nos.

10

Line constructed 

5,56,663 Km

11

Line energized

5,32,244 Km

12

Number of 33/11KV Sub-station & Capacity

1136 Nos. & 14,795 MVA

13

System loss (80 PBSs)

10.22% (12 Month Avg)

15.28 (This Month)

14

Monthly Sales

Tk 2000 Crore

15

Bill collection

98.79%

16

Peak demand

7100 MW

 

17. Consumer (By category):

1) LT-A (Domestic)

2,83,38,323

2) LT-B (Irrigation)

3,09,823

3) LT-C1 (Small Industry)

2,10,501

4) LT-C2 (Construction)

5,227

5)  LT-D1 (Charitable Institute)

3,95,374

6) LT-D2 (Street Light)

21,325

7) LT-D3 (Battery Charging Station) 7,474

7) LT-E (Commercial )

19,61,319

8) LT-T ( Temporary)

1,070

9) MT-1 ( Domestic)

242

10) MT-2 (Commercial)

1251

11) MT-3 (Industry )

13,886

12) MT-4 (Construction)

141

13) MT-5 (General)

527

14) MT-6 ( Temporary)

80

  MT-7 (11 KV Battery Charging Station) 5
  MT-8 (11 Kv Irrigation & Agriculture Pump) 43

15) HT-1 (General )

19

16) HT -2 ( Commercial)

2

17) HT-3 ( Industry )

472

18) HT-4 (Construction)

3

19) EHT-1 (General)

0

20) EHT-2 (General)

0

21) Solar 

13,424

Total

3,12,80,532

Ref: MIS March, 2021 & Line Construction Report April, 2021

 